  1. On the left side menu, go to project settings and choose the option Workflows. Then on the right-hand side, click the edit Edit button to edit your workflow. In this case, we will configure the post-function on the  

  2. Click Text view, then select the “in progress” transition. Move to the post-functions  

  3. Select the Post Functions tab, click to add post-function and then select then click Add Post Function.

  4. Select the "Copy/Move attachments (JSU)" post-function from the menuthen click Add.

  5. Configure the post function:
    1. Choose the Parent/Sub-task relation since you want the post
    -
    1. function to perform when the parent issue is transitioned and for the attachments to be copied on the sub-tasks.
     Select
    1.  
    2. Select the "always copy attachments" option from the drop-down menu
    of the configuration
    1. to have all the attachments you will add during the transition on the transition screen copied through to the sub-tasks. In this drop-down, you have the option to select a field of your parent issue to have a value, in order for the attachments to be copied to the sub-tasks. By configuring this, the attachments added on the transition screen will only be copied to the sub-tasks if that field has a value.
    2. Follow the same steps if you want the attachments that existed in your parent issue before the transition started to be copied through too.
     At the end of the page click the add button to add
    1.  
  6. Click Add to create your post-function. Do not forget to publish
  7. Publish your workflow.
  8. Now, go test your post function:
    1. Go to your issue and create sub-tasks for your team members. At this stage, you will need to assign a transition screen to the "
    in progress
    1. In Progress" transition in order to enable the rule you have configured in your post-function "copy/Move attachments added during the transition". Configuring screens is a functionality offered by Jira out of the box and here is a quick way of doing it for this case.
    Turn
    1. Move your parent issue
    in progress
    1. to "In Progress" and upload the creative document on the transition screen you created. Refresh and see what you have achieved with JSU! Open your sub-tasks and check your attachments. The document is there and now the whole team can start working without going back and forth to the parent issue.
Note

Attention! Make sure you edit the project's attachment permissions to be able to copy/move attachments.

Anchor
demo-video
demo-video
How-to video

Watch this video to see all of this in action*:

Widget Connector
width600
urlhttps://www.youtube.com/watch?v=UbCNZDGU-x0&t=5s
height350

This was only a bit sample of JSU in action. Subscribe to our YouTube channel and Access access more JSU use cases.
See also the app documentation for some more examples and configuration screenshots.

*The video is created on the Jira Server environment. 

...


Need more Information information or help? Get in touch!